STH 92, Mt. Horeb to Brooklyn

STH 92, Mt. Horeb to Brooklyn
Transportation | Construction Services

CORRE provided construction oversight and inspection services for this 7.3-mile pavement rehabilitation project which consisted of milling and paving STH 92 from Mt. Vernon to STH 69. The project included beam guard removal and replacement, grading, culvert pipe replacement, and pavement marking.

The project team successfully tackled any issues that arose during construction operations, including substantially revising traffic control to keep the roadway open during pipe replacement operations. They also improved site safety with the addition of numerous traffic control devices, facilitated lane closures, and sent out weekly updates to keep the traveling public safe and informed all while maintaining the project’s schedule and budget.

Key Elements/Deliverables
  • AASHTOWare Project
  • Construction project leader
  • Construction contract administration
  • Construction documentation
  • Construction inspection
  • Contract administration
  • Contract change orders
  • Electronic records documentation
  • Finals documentation
  • HMA testing and inspection
  • Lane Closure System
  • Materials technician/coordinator
  • Nuclear density testing
  • Pre-con and progress meetings
  • Progress estimates
  • Public involvement

Location: Dane County, WI
Client: WisDOT SW Region