I-41/43/894 Airport Freeway

I-41/43/894 Airport Freeway, 84th St to 35th St
Transportation | Construction Services

CORRE worked as a team with WisDOT and other firms to provide construction oversight and inspection services for this intricate project which consisted of rehabilitating I-894 Airport Freeway from 84th Street to 35th Street and reconstructing the Loomis Road (STH 36) bridge over I-894.

This multi-year improvement project involved reconstructing the shoulders of I-894; concrete base patching; resurfacing the freeway mainline and ramps; improving drainage systems; enhancing lighting and signing; and a full reconstruct of the Loomis Road bridge, ramps, and intersections. Pavement and maintenance for four local roads were also a part of this diverse project.

The project team solved numerous, extensive issues arising during grading operations and drainage system installation. CORRE facilitated communication between various teams to effectively resolve issues discovered in the field. Staff also maintained a safe site for the traveling public, construction staff, and contractors by proactively adjusting traffic control throughout the life of the project.

Key project components included staged construction, extensive storm sewer rehabilitation, grading operations, concrete barrier wall, base patching, temporary and permanent signing, temporary and permanent lighting, HMA pavement, concrete pavement, erosion control, two intersections with five freeway ramps, bridge painting, PPC overlays, sign structures, bridge maintenance, concrete surface repair, and curb and gutter.

CORRE provided all-encompassing HMA oversight, material coordination, density testing, and PWL coordination and documentation.

Location
Milwaukee County

Client
WisDOT SE Region

Construction Cost
$60 Million

Fast Facts

  • 3.3-mile urban rehab
  • Multi-year project
  • Highly-publicized weekend paving blitzes
  • Staged construction
  • Bridge reconstruction
  • 2 intersections
  • 5 freeway ramps on Loomis Road
  • Extensive storm sewer rehab and grading operations
  • Construction inspection, materials coordination and testing
  • Team coordination
  • Positive feedback from WisDOT