STH 58 Rehabilitation

STH 58 Rehabilitation
Transportation | Roadway Design

CORRE completed design work for this pavement replacement project north of Mauston in Juneau County. The scope included pre-milling the existing pavement, utilizing a cold-in-place recycle treatment of the remaining asphalt, and then overlaying the existing roadway. Design included evaluation of the existing beam guard to verify length of need was met and a field review of cross culverts to provide recommendations for replacement. Public involvement was a key factor with this project due to adjacent business concerns. Ninety percent PS&E documents were submitted six months early for this project which was completed in August of 2020.

Key Elements/Deliverables
  • Beam guard design
  • Design Study Report (DSR)
  • Environmental documentation
  • Final PS&E
  • Preliminary and final roadway plans
  • Public involvement
  • Roadway resurfacing design

Location: Juneau County, WI
Client: WisDOT SW Region
Construction Cost: $5M
Client Type: State Agency

STH 82, Mauston to I-39

STH 82, Mauston to I-39
Transportation | Construction Services

CORRE provided construction oversight and inspection services for this concrete pavement replacement project on STH 82 from STH 13 to CTH B. The project included common excavation, base aggregate dense, culvert pipe replacement, stringless concrete paving, HMA deck overlay, and restoration. Coordination with an adjoining project was critical for both projects in order to maintain access to local property. Successful project completion is a direct result of the partnership between all parties involved.

Key Elements/Deliverables
  • AASHTOWARE Project
  • Construction inspection
  • Contract administration
  • Contract modifications
  • Electronic records documentation
  • Finals documentation
  • GPS staking verification and survey
  • Incident management
  • Lane closure system
  • Materials testing and documentation
  • Mobile Inspector
  • OnStation App
  • Pre-con and progress meetings
  • Progress estimates
  • Project data/file management
  • Project management
  • Public involvement
  • RFI/DIN/WAF process

Location: Adams County, WI
Client: WisDOT North Central Region
Construction Cost: $5.7M
Client Type: State Agency

CTH S Reconstruction

CTH S Reconstruction
Specialty Services | Environmental

CORRE is completing design work for this approximately 3-mile-long roadway reconstruction and reconditioning project that consists of two segments. The southern segment involves pulverizing and overlaying the roadway and the northern segment involves full roadway realignment through the Vilas County forest.

In addition to roadway alignment and profile improvements, design includes reconstruction of several town road intersections to improve sight distance. Coordination with Vilas County, the Town of Conover and the Vilas County Forestry department is crucial. 

Design also includes culvert replacements and stream realignment. Extensive wetland delineation was required throughout the project limits. CORRE completed the Section 106 documentation, agency coordination, and wetland delineation for the project.

Key Elements/Deliverables
  • WDNR coordination
  • Wetland delineation report
  • Wetland field work
  • Section 106 documentation

Location: Vilas County, WI
Client: Vilas County, WI
Construction Cost: $2.75M
Client Type: State & Local Government

CTH S Bridge over the Grand River

CTH S Bridge over the Grand River
Transportation | Structure Design

This rural bridge replacement project consisted of minor approach reconstruction and the complete replacement of the existing structure that carries CTH B over the East Branch of the Eau Claire River. The bridge is located on a sag vertical curve within a large high-quality wetland area, meaning minimization of environmental impacts was crucial. Multiple steps to minimize impacts included using minimum design standards, modified standards, and several design exceptions. The new bridge, resting on Type A1 abutments supported by steel cast-in-place pipe piles driven to bearing, spans 40 feet over the East Branch of the Eau Claire River.

Key Elements/Deliverables
  • Categorical Exclusion Checklist (CEC)
  • Design Study Report (DSR)
  • Phase I HazMat assessment
  • PS&E
  • Public involvement

  • Roadway and structure plans
  • Section 404 permit
  • Survey
  • TMP Type 2
  • Utility coordination

Location: Green Lake County, WI
Client: Green Lake County, WI
Construction Cost: $363K
Client Type: State & Local Government

Short Street Reconstruction

Short Street Reconstruction
Transportation | Roadway Design

This project involved the redesign of Short Street to convert the 0.7-mile rural cross section city street into an urban section with a multi-use path and on-street bicycle lances. Prior to the 1970s, this roadway was formerly part of STH 37 and has since become a local city street. The roadway not only offers an important connection to state highways, but is one of four local street crossings over the Chippewa River which splits much of the city.

Project highlights included coordination with the WDNR due to the Chippewa River Trail crossing, grading for future bicycle connections to STH 37 and the Chippewa River trail, and completion of a flood analysis due to fill added within the Chippewa River floodplain.

Key Elements/Deliverables
  • Coordination with local municipality
  • Environmental documentation
  • Floodplain evaluation
  • Multi-modal design
  • Preliminary and final design plans
  • Real estate
  • Storm sewer design
  • Wetland determination

Location: Eau Claire County, WI
Client: City of Eau Claire
Construction Cost: $1M
Client Type: State & Local Government